PKP PLK delivers platforms of Railway Station

September 3, 2013 Katowice the City 0

On the 2nd of September, the platform 1 of the Katowice Railway Station was delivered and put at passengers disposal. This way the last stage of the modernization process of the Station’s platforms was concluded.

A new surface, elements of small architecture, information system for passengers and fittings were built within the general modernization of the platforms. The redevelopment included the installation of new power grids and a water-supply-and-sewage system.

No Image

Neinver talks about office building at Szewczyka Sq.

May 18, 2013 Katowice the City 0

While the last works are being carried out on Galeria Katowicka and the mall is scheduled to be opened in September this year, questions will surely be asked more and more often about the last stage of Neinver’s multipurpose undertaking – the office building at Szewczyka Sq. Now the investor updates the project’s status.

The facility is planned to be erected at the east side of the construction plot on Młyńska St., very close to the

No Image

New road and more glass

March 15, 2013 Katowice the City 0

At the beginning of March, construction works were launched on a new road connecting Młyńska and Dworcowa streets. The route will be located along the planned office building to be raised within the Neinver’s multipurpose complex.

The new road will help to improve the traffic in the area of the City Hall and Szewczyka Sq. This 4,5 meters wide one-way street will be about 100 meters long. It is planned to deliver the new route in August this year.

No Image

Steel construction covers platform 4

March 7, 2013 Katowice the City 0

Builders of the platform 4 are finishing to erect the steel structure of the roof at the Katowice Railway Station. The works were relaunched at the beginning of 2013 after necessity of changing one of sub-contractors.

Previously, the construction over all four platforms was planned to be delivered by the end of the last year. Due to a bankruptcy of Budus, the subcontractor of the undertaking, the works are delayed. The PRK Kraków prime contractor has already chosen