Three tower cranes, carrying about 140 tons of construction materials daily, a 87 000 cubic meters excavation site, more than 5 000 cubic meters of soil being removed every day, 310 workers – these are present numbers concerning the extension of Silesia City Center.
Since the beginning of January, the tower cranes work on foundations and an underground car park of new SCC. Two of these machines can reach a maximum radius of 50 meters, the third one has a working radius of 60 meters. Construction works on foundations will last to spring when a fourth stage of works is scheduled for completion.
The extended part of Silesia City Center will be opened in autumn 2011. It is going to add 20 000 sq. meters of retail space to the existing 66 000 sq. meters. By now, 11 new tenants were confirmed.