A cornerstone was laid at the construction site of Galeria Libero in October. Echo Investment, an investor of the shopping and entertainment center has also informed about a new tenant.

The company celebrated the cornerstone laying in the presence of its CEO, Nicklas Lindberg. This way the developer kicked-off the construction work formally. The works are being conducted by Erbud. It is expected …

No Image

Shell of Galeria Libero for PLN 75 milion

September 7, 2016 Katowice the City 0

Erbud was named a prime contractor of the shell of Galeria Libero, which is being developed by Echo Investment in the southern part of Katowice.

Echo Investment concluded a contract with Erbud concerning the construction of the Galeria Libero’s shell. The contract amounts to net PLN 75 million. The prime contractor is obliged to finish the works by 14th of September …

No Image

Shell completed of multidisciplinary hospital

February 6, 2015 Katowice the City 0

White elevation has recently been emerged on a multidisciplinary hospital called Geo Medical. Prime contractor already crossed half-way mark of works.

The construction of the project was inaugurated in July 2013 and was divided into stages. The multidisciplinary hospital will consist of three 6-storey buildings housing 15 wards (offering 230 hospital beds in total) and an operating department with …

No Image

Erbud contracted to build new medical facilities

January 12, 2015 Katowice the City 0

Erbud won another contract for development of medical infrastructure in Katowice. The company will build and expand the Stanisław Leszczyński Memorial Hospital located at 26 Raciborska St.

According to the contact, Erbud will be involved in the first stage of construction works on a new 4-storey building of operating suites. Also, the prime contractor will extend two existing …