No Image

Works half-way marked on ICC

March 13, 2014 Katowice the City 0

Nine months left to conclude the construction work on the International Convention Center (ICC). The building is now almost half-finished.

Currently 450 workers of Warbud and its subcontractors are engaged at the construction site working on a three 8-hour shift basis to provide around the clock coverage. At the beginning of March, builders finished works on the steel structure of the roof and facades, of which the weight …

No Image

ICC emerges from behind Spodek

October 23, 2013 Katowice the City 0

The construction site of the International Convention Center (ICC) was handed over to Warbud and Mercury Engineering in June this year when the construction was 6% advanced. Today the building takes its shape more and more every day and the advancement of works helps to imagine the scale of the ICC.

Construction crews reached the top of the center on the north side where the roof is being laid over the multifunctional hall for 12 000 spectators.

No Image

Works pick up steam on ICC

July 10, 2013 Katowice the City 0

More and more workers and building machinery appear at the construction site of the International Convention Center. One month after the site has been handed over to Warbud, concrete and steel fixing works are increasingly advanced.

The consortium of Warbud and Mercury Engineering was contracted by the City Hall of Katowice in May. The prime contractor is obliged to erect the ICC by 3rd of October 2014. To keep the schedule, the consortium